Constructions in progress

picture

EXPANSION OF THE PRODUCTION AREA OF MANN+HUMMEL INNENRAUMFILTER (CZ) S.R.O., UHERSKÝ BROD

Drywalls are being constructed at the moment. Ventilation systems, electrical installations, sanitary installations, external sewage and assembly of the steel structures proceeds.

picture
29.5.2023

EXTENSION OF THE EXISTING ASSEMBLY HALL AND ADMINISTRATIVE BUILDING OF SEW EURODRIVE CZ s.r.o., HOSTIVICE NEAR PRAGUE

Site inspection was successfully conducted with the participation of a representative of the Hostivice building authority and a Fire Brigade authority at the end of May. A positive opinion of the F.B. authority will be issued during the following days and subsequently the building authority will issue a Permission of the trial operation. Most of the construction works have been completed. Minor snags are being fixed. Following work are in progress: the floors joints, installation of the stainless steel thresholds and lacquered parapets, preparation for epoxy coating on the walkway of the production hall, preparation for the application of Venetian stucco at the main staircase, the fencing of the compound is also being completed and landscaping works continue.

picture
29.5.2023

Reconstruction and extension works of the Rokoska apartment building with the added elevator, Prague 8 Libeň

A glass passenger lift was put into operation. The terrazzo on the staircase was completed and the entrance doors to the apartments were installed. The installation of internal interior doors and wooden floors, the completion of sanitary ware and electrical end elements is in progress. A new internal stair railing will be installed in the near future. The modification of the external paved areas was completed – the sidewalk along Nad Rokoskou street and the parking space at the apartment building. Installation of external fencing and shelter for municipal waste is underway. An authorized noise measurement was carried out, which is a condition for the successful approval of the apartment building. In the following weeks, an inspection by the Fire Brigade authority and the Regional Hygiene Station is planned, followed by a local investigation by the building authority.