30.10.2019 | Constructions in progress
The building was successfully completed and handed over for use by the owner.
12.7.2019 | Constructions in progress
Opening Ceremony was held for the participation of the French Ambassador in the Novares Janovice production area. Finishing works are underway.
| Constructions in progress
Ceremonial opening of the new plant in Prostějov
| Constructions in progress
The office building is completed, furniture and gastronomic equipment are being installed. The last stage of the epoxy floor screed is being executed in the production hall. Individual production machines are being connected to media. The installation of final elements of Ventilation distribution system and thermal insulation is going on. Furthermore, the installation of BMS technology is under realization. The cladding of external warehouse on the J / 3 - 9 axis has been completed, mounting of the MEP installations of this warehouse proceeds. Investor‘s suppliers are completing the installation of their technological systems and machinery equipment.
10.8.2018 | Constructions in progress
The reconstruction of the halls has been completed
14.4.2018 | Constructions in progress
The over-structure has been finished and handed over to the client.
| Constructions in progress
MHIS – The exhibition and conference hall at GUtech project in the Sultanate of Oman succesfully completed
| Constructions in progress
Construction of a new logistic hall Windmöller & Hölscher Czech Ltd. in the industrial zone of Prostejov has been finished.
| Constructions in progress
10.2.2016 | Constructions in progress
Construction of the new logistics hall GZ Media, Loděnice near Beroun
14.7.2015 | Constructions in progress
Reconstruction of terraced prefabricated house from 1990 in Prague 8
7.4.2015 | Constructions in progress
Finishing utilities and cladding proceed. Furthermore, assembly technology, windows and doors. Surface finishes of outbuildings and in-building and backfilling behind the supporting walls have begun.
11.11.2014 | Constructions in progress
Concreting of the foundation slab has been finished in place of conveyors and foundations for chimeny filter. Currently, the construction of reinforced concrete walls on axis 1/ D-G and walls for conveyors proceed.Realization of high voltage connection has been started.
| Constructions in progress
Tha construction has benn completed and handed over to the investor.
4.4.2014 | Constructions in progress
Construction of the new builing has been successfully completed as scheduled.
| Constructions in progress
The construction has been successfully approved and it is currently in the process of handover and removing small backlogs.
10.7.2013 | Constructions in progress
Construction of Industrial Park Ronal in Walbrzych is now near completion. Test run of production facilities was successfully completed in the first half of March. Currently finishing construction works proceed in technical space, office and sanitary facilities to handover to the client for use. Working on ceilings, paintings, installation of doors, sanitary partitions, furnishing facilities, kitchens etc. Fitting distributions for the recovery of energy production technology proceed.
24.7.2013 | Constructions in progress
Assembly of prefabricated reinforeced concrete structure has been completed. Installation of the roof corrugated steel sheets and the facade has begun.
23.7.2013 | Constructions in progress
In June the building inspection and commissioning successfully held and trial operation of heat and electric energy has been started.